Solar Thermal Heat Exchanger Sizing: Duty, Approach Temperature and Glycol Effects
Solar thermal · Hydraulic design
Solar Thermal Heat Exchanger Sizing: Duty, Approach Temperature and Glycol Effects
A solar thermal heat exchanger should be specified by its operating conditions. A quotation marked “50 kW” leaves unanswered whether that duty is achievable with your collector-loop temperature, storage return temperature, glycol mixture and available pump pressure.

In this guide
This guide helps EPC engineers and technical buyers prepare a duty sheet for an external liquid-to-liquid exchanger, then check whether competing selections answer the same requirement. Start with a hydraulic drawing, a defined operating case and the fluid information for both circuits. The result is a specification a manufacturer can calculate against.
For the broader decisions about collector area, storage and backup heat, use the commercial solar water heating sizing guide. Here, the calculation boundary is the exchanger itself.
1. Define the operating case before entering a heat load
Name the case you want the exchanger to satisfy: for example, charging storage under a stated collector inlet condition. Record which conditions are fixed and which the supplier may calculate. Asking for a fixed heat load, four fixed temperatures and two arbitrary fixed flows can create an inconsistent specification.
Alfa Laval's calculation method identifies duty, temperatures, flows, allowable pressure drops and operating limits as essential selection inputs. Translate those inputs into the following project worksheet.
| Duty-sheet field | Hot circuit: solar loop | Cold circuit: receiving loop |
|---|---|---|
| Circuit identification | Drawing reference and flow direction | Drawing reference and flow direction |
| Fluid | Product name, glycol type and concentration basis | Water or other fluid; relevant chemistry |
| Inlet temperature | Tₕ,in, °C; fixed or calculated | T𝚌,in, °C; fixed or calculated |
| Outlet temperature | Tₕ,out, °C; fixed or calculated | T𝚌,out, °C; fixed or calculated |
| Flow | kg/s or m³/h; state temperature for volume | kg/s or m³/h; state temperature for volume |
| Allowable exchanger pressure loss | kPa at the stated flow and fluid condition | kPa at the stated flow and fluid condition |
| Mechanical limits | Required design pressure and temperature envelope | Required design pressure and temperature envelope |
| Service information | Fluid condition, cleaning and isolation provisions | Water quality, fouling basis and maintenance access |
Write the required transferred duty in kW above the table. Add separate cases where relevant, such as warm storage return, reduced solar input or cold startup. A daily energy requirement in kWh cannot be entered directly as an instantaneous exchanger duty in kW.
Completion check: another engineer should be able to identify the exact duty case without guessing which temperature or flow may change.
2. Reconcile the heat balance on both sides
For a steady, single-phase calculation with approximately constant specific heat:
Hot-side duty = ṁh × cp,h × (Th,in − Th,out) Cold-side duty = ṁc × cp,c × (Tc,out − Tc,in) ṁ in kg/s; cp in kJ/(kg·K); temperature difference in K Result: kW
The two duties should agree when external heat loss is neglected. If volume flow is supplied, first convert it using the fluid density at the relevant condition. Where properties vary materially, use the fluid enthalpy difference instead of a single constant heat capacity. The underlying heat balance and volume-to-mass conversion are described in Alfa Laval's heat-transfer theory guide.
For a hypothetical 50 kW water duty, assume a constant heat capacity of 4.18 kJ/(kg·K) and a 10 K change:
Required mass flow = 50 ÷ (4.18 × 10) = 1.196 kg/s
If someone enters only 0.80 kg/s for that same side, the stated temperatures imply 33.44 kW. Increasing the exchanger's catalogue rating cannot make those inputs consistent. Decide whether flow, outlet temperature or duty is allowed to change, and revise the sheet.
Keep calculated values visibly separate from measured inputs. This makes later quotation revisions traceable and prevents an assumption from becoming a purported site reading.
3. Check the temperature approach at both ends
For the counterflow arrangement below, compare the hot inlet with the cold outlet, and the hot outlet with the cold inlet. Do not confuse either end difference with the temperature change within one circuit.
Scroll horizontally to inspect the full diagram →
ΔT1 = Th,in − Tc,out ΔT2 = Th,out − Tc,in LMTD = (ΔT1 − ΔT2) ÷ ln(ΔT1 / ΔT2)
When the two end differences are equal, LMTD equals that common difference. In this simple counterflow model, both must be positive for a finite-area exchanger to transfer the stated sensible heat in the intended direction. The manufacturer calculation method uses these same terminal pairings.
Same 50 kW, different thermal difficulty
The following is an original teaching comparison. Both sides use the constant water heat capacity assumed above, with negligible external losses. These are two required duties, not two tests of a SOLETKS product.
| Input or calculated result | Case A | Case B |
|---|---|---|
| Required transfer | 50 kW | 50 kW |
| Hot inlet → outlet | 80 → 70°C | 65 → 55°C |
| Cold inlet → outlet | 40 → 50°C | 50 → 60°C |
| Each side's temperature change | 10 K | 10 K |
| Each side's mass flow | 1.196 kg/s | 1.196 kg/s |
| End differences ΔT1 / ΔT2 | 30 / 30 K | 5 / 5 K |
| LMTD | 30 K | 5 K |
| Required UA, calculated as duty ÷ LMTD | 1.67 kW/K | 10.0 kW/K |
Case B requires six times the conductance, UA, under these assumptions. It does not establish six times the plate area: U also depends on the selected exchanger and operating conditions. Notice that Case B's cold outlet is warmer than the hot outlet; this is compatible with counterflow because the local end differences remain positive.
For unequal positive end differences of 20 K and 10 K, LMTD is approximately 14.43 K. This illustrates why simply averaging the two numbers gives a different result.
4. Replace water assumptions with the actual glycol mixture
Record the inhibited fluid's product name, base glycol, concentration and whether that concentration is by mass or volume. Use properties for the working mixture at its operating temperatures. TYFOROP's TYFOCOR L technical bulletin, hosted by RESOL, illustrates separate temperature-and-concentration dependencies for density, viscosity, heat capacity and conductivity. It is a historical bulletin; obtain the current data for the fluid actually specified.
These properties answer different questions. Heat capacity and density support the heat balance and flow conversion. Viscosity and conductivity are also needed for thermal and hydraulic selection. A water calculation followed by an unexplained percentage allowance does not document those effects.
As a sensitivity exercise only, replace 4.18 with an assumed heat capacity of 3.80 kJ/(kg·K):
50 ÷ (3.80 × 10) = 1.316 kg/s
The required mass flow is about 10% higher. The value 3.80 is not assigned to a particular glycol product or concentration. This exercise does not calculate exchanger pressure loss or plate count.
Ask for a fresh selection using the named mixture. Alfa Laval's PHE Select explicitly distinguishes supported water and glycol duties; use the selected manufacturer's applicable tool and fluid library. Have the supplier flag any fluid or operating case outside that library.
5. Coordinate pressure loss, materials and service access
An exchanger's pressure-loss allowance is only its share of the circuit resistance. Keep the collector field, pipework, valves, strainers and other components in the pump calculation. Also distinguish allowable pressure loss through the exchanger from its pressure rating.
Thermal performance and hydraulic resistance interact through channel design. The Alfa Laval theory guide explains this tradeoff and distinguishes openable gasketed units from brazed or fusion-bonded constructions. Therefore, compare the proposed thermal and hydraulic results together and check whether the maintenance method fits the plant room.
Provide the water analysis and material restrictions instead of specifying “stainless steel” alone. Plates, joining materials and seals all need consideration. Alfa Laval's HVAC technical FAQ discusses how debris can obstruct narrow channels and why fluid chemistry matters to material selection. Have the supplier document compatibility for the actual circuits, including any applicable potable-water requirements.
Before accepting a layout, mark the isolation, drain, cleaning and removal access on the drawing. An exchanger that fits between two pipes may still be inaccessible for service.
6. Compare quotations against one unchanged duty sheet
Use the same revision of the input sheet for every supplier. The following fictional comparison shows how to review a selection without guessing which product is “better.”
| Review item | Selection A | Selection B | Engineering action |
|---|---|---|---|
| Temperature program | Matches Case B | Matches Case A | Recalculate B at Case B before comparing |
| Solar-side fluid | Named project mixture | Water | Recalculate B with the project fluid |
| Pressure loss | Reported for both circuits | One combined figure | Obtain separate circuit results |
| Fouling/design allowance | Defined | Unstated | Agree a common basis |
| Mechanical and service details | Documented | Incomplete | Resolve before equipment acceptance |
The review is complete when the supplier calculation reproduces the agreed duty case, both pressure losses fit the pump design, and material and service requirements are documented. Keep unresolved assumptions attached to the selection rather than hiding them in a price comparison.
For a SOLETKS solar thermal integration discussion, send the hydraulic drawing, completed duty sheet, fluid data and relevant operating cases. For factory applications, the factory solar hot water guide provides the surrounding system context.
Discuss your project
